Connection Fee:
a) Base connection fee | |
In case of connection to the low voltage / 0, 4 kV-more than 32 A /supply network: | |
In case of direct connection to mid/low voltage (20kV/0,4kV)supply point: | |
In case of connection to the mid voltage (20kV) supply network: | |
- In case of direct connection to high/mid voltage (120 kV/20/kV) or mid/mid voltage supply point in the power substation for mid-voltagesupply: |
b) Construction costs of connecting cables are additional to the base connection fee: | |
Overhead cable: over length of 30 m max.: | |
Underground cable: over length 15 m max.: |
c) Construction costs of public cables are additional to the base connection fee: | |||
Low voltage overhead cable: | Low voltage underground cable: | ||
Mid voltage overhead cable: | Mid voltage underground cable: |
Infrastructure development contribution (connection fee): | |
Firewater (availability): |
Infrastructure development contribution (connection fee): |
Infrastructure development contribution (connection fee), as agreed: |
x contracted consumption gas quantity (Nm3/h) |